fix(#2388): gate shared requirement completion on sibling plans, revert on gaps (#2424)

* fix(#2388): gate shared-ID requirement marking and revert on gaps_found

Adds requirements.ready-ids (execute-plan.md's update_requirements step)
so a requirement ID declared by multiple plans in a phase only marks
Complete once every declaring plan has produced a SUMMARY.md, and
requirements.revert-phase (execute-phase.md's gaps_found branch) so a
gaps_found verdict reverts the phase's own prematurely-Complete IDs
before the gap report renders. Single-plan IDs still mark immediately.

Co-Authored-By: Claude Opus 4.8 <noreply@anthropic.com>

* chore(#2388): regenerate fixtures + lint gate-prep

* fix(#2388): repair failing tests after gate verification

* chore(#2388): add changeset (#2424)

---------

Co-authored-by: Claude Opus 4.8 <noreply@anthropic.com>
This commit is contained in:
Tom Boucher
2026-07-19 07:52:17 -04:00
committed by GitHub
parent b2f4aa9435
commit 8d2f8bcb23
47 changed files with 534 additions and 61 deletions

View File

@@ -24,8 +24,8 @@
"docs-update.md": 55706,
"edit-phase.md": 12927,
"eval-review.md": 9967,
"execute-phase.md": 93363,
"execute-plan.md": 33113,
"execute-phase.md": 93376,
"execute-plan.md": 34262,
"explore.md": 10541,
"extract-learnings.md": 12893,
"fast.md": 7613,