docs(16): create phase plan
Phase 16: Plan Verification Loop - 3 plan(s) in 2 wave(s) - Wave 1: 16-01 (create gsd-plan-checker agent) - Wave 2: 16-02, 16-03 (parallel - orchestrator + planner revision) - Ready for execution Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>
This commit is contained in:
@@ -19,19 +19,19 @@
|
||||
|
||||
## Current Position
|
||||
|
||||
Phase: 15 of 15 (Dedicated Planner Agent)
|
||||
Plan: 1 of 2 in current phase
|
||||
Status: In progress
|
||||
Last activity: 2026-01-16 - Completed 15-01-PLAN.md
|
||||
Phase: 16 of 16 (Plan Verification Loop)
|
||||
Plan: 0 of 3 in current phase
|
||||
Status: Planned
|
||||
Last activity: 2026-01-16 - Phase 16 planned (3 plans in 2 waves)
|
||||
|
||||
Progress: ██████████████████████████████ 34/35 plans (97%)
|
||||
Progress: ██████████████████████████████ 36/36 plans (100%)
|
||||
|
||||
## Performance Metrics
|
||||
|
||||
**Velocity:**
|
||||
- Total plans completed: 34
|
||||
- Average duration: 3.5 min
|
||||
- Total execution time: ~120 min
|
||||
- Total plans completed: 36
|
||||
- Average duration: 3.4 min
|
||||
- Total execution time: ~122 min
|
||||
|
||||
**By Phase:**
|
||||
|
||||
@@ -51,10 +51,10 @@ Progress: ███████████████████████
|
||||
| 99 | 3 | 1 min | <1 min (parallel) |
|
||||
| 13 | 3 | 10 min | 3.3 min |
|
||||
| 14 | 3 | 11 min | 3.7 min |
|
||||
| 15 | 1 | 5 min | 5 min |
|
||||
| 15 | 3 | 7 min | 2.3 min |
|
||||
|
||||
**Recent Trend:**
|
||||
- Last 5 plans: 14-01 (4m), 14-02 (4m), 14-03 (3m), 15-01 (5m)
|
||||
- Last 5 plans: 14-03 (3m), 15-01 (5m), 15-02 (3m), 15-03 (1m)
|
||||
- Trend: Consistent execution times
|
||||
|
||||
*Updated after each plan completion*
|
||||
@@ -89,6 +89,9 @@ Progress: ███████████████████████
|
||||
| 14 | Parallel agent spawning for /gsd:research-project | 4 agents (stack, features, architecture, pitfalls) maximize throughput |
|
||||
| 15 | 1,147 lines from ~3,580 source (68% reduction) | Complete planning methodology consolidated into single agent |
|
||||
| 15 | 14 sections covering full planning workflow | Includes discovery, task breakdown, dependency graph, goal-backward, checkpoints, TDD, gap closure |
|
||||
| 15 | Deprecation notices point to specific agent sections | Planning references deprecated, content in gsd-planner |
|
||||
| 15 | 189 lines thin orchestrator for /gsd:plan-phase | Under 200 target, uses agent: gsd-planner frontmatter |
|
||||
| 15 | Context-only planner-subagent-prompt.md template | Follows debug/research template pattern |
|
||||
|
||||
### Deferred Issues
|
||||
|
||||
@@ -112,16 +115,17 @@ None yet.
|
||||
- Phase 13 added: Dedicated debug agent (gsd-debugger with baked-in expertise, thin orchestrator pattern)
|
||||
- Phase 14 added: Dedicated researcher agent (gsd-researcher with research methodology, tool strategy, output formats)
|
||||
- Phase 15 added: Dedicated planner agent (gsd-planner with planning expertise, refactor plan-phase to thin orchestrator)
|
||||
- Phase 16 added: Plan verification loop (gsd-plan-checker, planner → checker → revise orchestration)
|
||||
|
||||
## Project Alignment
|
||||
|
||||
Last checked: 2026-01-16
|
||||
Status: IN PROGRESS
|
||||
Assessment: Phase 15 Plan 01 complete, Plan 02 (thin orchestrator refactor) remaining.
|
||||
Status: ON TRACK
|
||||
Assessment: Phase 16 added. Plan verification loop — planner → checker → revise orchestration before execution.
|
||||
Drift notes: None
|
||||
|
||||
## Session Continuity
|
||||
|
||||
Last session: 2026-01-16
|
||||
Stopped at: Completed 15-01-PLAN.md
|
||||
Stopped at: Completed 15-03-PLAN.md
|
||||
Resume file: None
|
||||
|
||||