Tasks completed: 3/3 - Create Mill build configuration - Create project structure and configuration - Create HTTP routes and Main entry point SUMMARY: .planning/phases/01-foundation/01-01-SUMMARY.md
1.7 KiB
1.7 KiB
Project State
Project Reference
See: .planning/PROJECT.md (updated 2026-02-04)
Core value: A CMF that enables rapid application development with the flexibility to support any use case, delivered with the performance and horizontal scaling that PHP cannot provide. Current focus: Phase 1 - Foundation
Current Position
Phase: 1 of 10 (Foundation) Plan: 1 of 3 in current phase Status: In progress Last activity: 2026-02-04 - Completed 01-01-PLAN.md
Progress: [#.........] 3% (1/29 plans)
Performance Metrics
Velocity:
- Total plans completed: 1
- Average duration: 39 min
- Total execution time: 0.65 hours
By Phase:
| Phase | Plans | Total | Avg/Plan |
|---|---|---|---|
| 01 | 1 | 39min | 39min |
Recent Trend:
- Last 5 plans: 01-01 (39min)
- Trend: Baseline established
Updated after each plan completion
Accumulated Context
Decisions
Decisions are logged in PROJECT.md Key Decisions table. Recent decisions affecting current work:
- [Roadmap]: Comprehensive depth selected (10 phases, 29 plans)
- [Roadmap]: Plugin System identified as architectural bottleneck - Phase 2
- [Research]: Quill for database (compile-time SQL validation), ScalaTags + HTMX for frontend
- [01-01]: Mill 1.1.1 required for Java 25 compatibility (ASM class file version 69)
- [01-01]: Use root.config import to avoid zio.config shadowing
Pending Todos
None yet.
Blockers/Concerns
- Research flag: Plugin System (Phase 2) needs deep research before planning
- Research flag: Admin Backend (Phase 7-8) has hidden complexity (YAML edge cases)
Session Continuity
Last session: 2026-02-04 Stopped at: Completed 01-01-PLAN.md (Mill Build and ZIO HTTP Server) Resume file: None