docs(17-06): advance state and roadmap after the unit tests and phase gate plan

This commit is contained in:
2026-10-12 19:54:11 +02:00
parent 3a0c4f72d7
commit 073fd129f9
2 changed files with 15 additions and 11 deletions

View File

@@ -1075,7 +1075,7 @@ Plans:
4. grzybyfunkcjonalne.pl reads its menu and FAQ from the plugins instead of app config.
5. The new code has unit tests, delivered in the phase's last plan.
**Plans:** 5/6 plans executed
**Plans:** 6/6 plans executed
Plans:
**Wave 1**
@@ -1094,7 +1094,7 @@ Plans:
**Wave 4** *(blocked on Wave 3 completion)*
- [ ] 17-06-PLAN.md — Unit tests across all repositories, scripts/check-phase17.sh and the validation map
- [x] 17-06-PLAN.md — Unit tests across all repositories, scripts/check-phase17.sh and the validation map
### Phase 18: Payment Gateway
@@ -1320,7 +1320,7 @@ Phases execute in numeric order: 1 → 2 → 3 → 4 → 5 → 6 → 7 → 8 →
| 14.3. One-command app scaffolding (INSERTED) | 4/4 | In Progress| |
| 15. Journal plugin | 4/4 | Complete | 2026-10-06 |
| 16. grzybyfunkcjonalne.pl on reusable blog views | 5/5 | In Progress| |
| 17. Blog companions | 5/6 | In Progress| |
| 17. Blog companions | 6/6 | In Progress| |
| 18. Payment Gateway | 0/TBD | Not started | - |
| 18.1. Payment Gateway Subscriptions | 0/TBD | Not started | - |
| 19. Chat and ChatChannels | 0/TBD | Not started | - |

View File

@@ -3,17 +3,17 @@ msd_state_version: "1.0"
milestone: v1.0
current_phase: 17
current_phase_name: Blog companions
status: executing
stopped_at: Completed 17-05-PLAN.md
last_updated: "2026-10-12T16:56:25.758Z"
status: verifying
stopped_at: Completed 17-06-PLAN.md
last_updated: "2026-10-12T17:53:57.388Z"
last_activity: 2026-10-12
last_activity_desc: Phase 17 execution started
state_head: 134e6640f1ffb577c9c69cecc28a139a42ce3cca
state_head: 3a0c4f72d799d0c1051fb21bbb22627e33dfe72c
progress:
total_phases: 40
completed_phases: 14
total_plans: 168
completed_plans: 167
completed_plans: 168
gsd_state_version: "1.0"
milestone_name: milestone
---
@@ -31,7 +31,7 @@ See: .planning/PROJECT.md (updated 2026-10-12)
Phase: 17 (Blog companions) — EXECUTING
Plan: 6 of 6
Status: Ready to execute
Status: Phase complete — ready for verification
Last activity: 2026-10-12 — Phase 17 execution started
Progress: [████░░░░░░] 44%
@@ -224,6 +224,7 @@ Progress: [████░░░░░░] 44%
| Phase 17 P03 | 38 min | 4 tasks | 53 files |
| Phase 17 P04 | 32min | 5 tasks | 70 files |
| Phase 17 P05 | 93min | 5 tasks | 103 files |
| Phase 17 P06 | 53 min | 4 tasks | 50 files |
## Accumulated Context
@@ -739,6 +740,9 @@ Recent decisions affecting current work:
- [Phase 17]: 17-05: grzybyfunkcjonalne menu code main-menu; Winter menu types map by the built-in link->url and blog_categories->all-journal-categories, no --map; six orphan link entries dropped
- [Phase 17]: 17-05: sitemap:import-winter --page-url copies a Winter cms-page item as a url item (blog=/blog on grzybyfunkcjonalne); the PHP site had no sitemap settings, plugin defaults apply
- [Phase 17]: 17-05: UAT remote checks run on the server through nginx with curl --resolve to loopback; production deploy and summercms.go push not approved
- [Phase 17]: 17-06: cabana singleton route reruns its transaction once on a Postgres unique violation from SingletonRecord (first-open race); fix 6312929 needs the next framework tag
- [Phase 17]: 17-06: scripts/check-phase17.sh is the Phase 17 gate; every Phase 17 test name sits in one stage list (go, plugins, admin, layers, postgres)
- [Phase 17]: 17-06: protocol-relative menu URLs stay anchors (D-16 rule) in the server and layer; the plan's text-without-href wording is a deferred question
### Pending Todos
@@ -815,6 +819,6 @@ Items acknowledged and carried forward from previous milestone close:
## Session Continuity
Last session: 2026-10-12T16:56:24.936Z
Stopped at: Completed 17-05-PLAN.md
Last session: 2026-10-12T17:53:56.658Z
Stopped at: Completed 17-06-PLAN.md
Resume file: None