docs(08-10): complete coverage, security review and final gate plan
Phase 8 closed on user approval (Playwright UI matrix gap carried forward). AUTH-05/06/07 marked complete; ROADMAP and STATE reflect 10/10 plans done.
This commit is contained in:
@@ -20,7 +20,7 @@ Decimal phases appear between their surrounding integers in numeric order.
|
||||
- [x] **Phase 5: Data layer full fidelity** - All 25 models and their squashed migrations with fillable/hidden/cast/soft-delete discipline (completed 2026-09-18)
|
||||
- [x] **Phase 6: HTTP routing, auth groups and rate limiting** - Three auth groups, named rate buckets, OAuth-safe middleware structure (completed 2026-09-21)
|
||||
- [x] **Phase 7: User plugin and authentication** - Registration, login, JWT, organizations, personal tokens, must-change-password (completed 2026-09-22)
|
||||
- [ ] **Phase 8: OAuth2.1 authorization server** - direct standard-library `wristband` server for fonoteka-mcp and the ChatGPT connector
|
||||
- [x] **Phase 8: OAuth2.1 authorization server** - direct standard-library `wristband` server for fonoteka-mcp and the ChatGPT connector (completed 2026-09-23)
|
||||
- [ ] **Phase 9: Backend admin authentication and schema pipeline** - Admin roles, fields.yaml/columns.yaml, relation manager
|
||||
- [ ] **Phase 10: Admin Vue SPA** - Login, navigation, lists, forms and relation manager for five controllers
|
||||
- [ ] **Phase 11: Jobs, realtime and search infrastructure** - River, Centrifugo and Typesense sync brought up before the API phases that need them
|
||||
@@ -358,7 +358,7 @@ Plans:
|
||||
|
||||
**Wave 9** *(blocked on 08-09; blocking security checkpoint)*
|
||||
|
||||
- [ ] 08-10-PLAN.md — Close 103-method coverage, independent security review, and the final fail-closed gate
|
||||
- [x] 08-10-PLAN.md — Close 103-method coverage, independent security review, and the final fail-closed gate
|
||||
|
||||
### Phase 9: Backend admin authentication and schema pipeline
|
||||
|
||||
@@ -496,7 +496,7 @@ Phases execute in numeric order: 1 → 2 → 3 → 4 → 5 → 6 → 7 → 8 →
|
||||
| 5. Data layer full fidelity | 6/6 | Complete | 2026-09-18 |
|
||||
| 6. HTTP routing, auth groups and rate limiting | 14/14 | Complete | 2026-09-21 |
|
||||
| 7. User plugin and authentication | 8/8 | Complete | 2026-09-23 |
|
||||
| 8. OAuth2.1 authorization server | 9/10 | In Progress| |
|
||||
| 8. OAuth2.1 authorization server | 10/10 | Complete | 2026-09-23 |
|
||||
| 9. Backend admin authentication and schema pipeline | 0/TBD | Not started | - |
|
||||
| 10. Admin Vue SPA | 0/TBD | Not started | - |
|
||||
| 11. Jobs, realtime and search infrastructure | 0/TBD | Not started | - |
|
||||
|
||||
Reference in New Issue
Block a user