docs(09-09): complete styles admin controller plan

This commit is contained in:
Jakub Zych
2026-09-26 15:10:18 +02:00
parent e9c0722337
commit 53d59dbc92
3 changed files with 208 additions and 15 deletions

View File

@@ -1,20 +1,21 @@
---
gsd_state_version: "1.0"
gsd_state_version: 1.0
milestone: v1.0
milestone_name: milestone
current_phase: 09
current_phase_name: Backend admin authentication and schema pipeline
status: executing
stopped_at: Completed 09-08-PLAN.md
last_updated: "2026-09-26T01:03:13.475Z"
last_activity: 2026-09-25
last_activity_desc: Phase 09 execution started
state_head: e6d013717faf3d4ac1e63036877688ca0cbfc128
stopped_at: Completed 09-09-PLAN.md
last_updated: "2026-09-26T13:09:59.401Z"
last_activity: 2026-09-26
last_activity_desc: Phase 09 execution continued through the Styles controller
state_head: e9c07223376519f1636dad557cccb6cf0ddd1604
progress:
total_phases: 15
completed_phases: 8
total_plans: 67
completed_plans: 63
milestone_name: milestone
completed_plans: 64
percent: 96
---
# Project State
@@ -29,11 +30,11 @@ See: .planning/PROJECT.md (updated 2026-09-16)
## Current Position
Phase: 09 (Backend admin authentication and schema pipeline) — EXECUTING
Plan: 9 of 12
Plan: 10 of 12
Status: Ready to execute
Last activity: 2026-09-25 — Phase 09 execution started
Last activity: 2026-09-26
Progress: [██████████] 100%
Progress: [██████████] 96%
## Performance Metrics
@@ -117,6 +118,7 @@ Progress: [██████████] 100%
| Phase 09 P06 | 29min | 3 tasks | 15 files |
| Phase 09 P07 | 2h20m | 2 tasks | 9 files |
| Phase 09 P08 | 2h28m | 2 tasks | 4 files |
| Phase 09 P09 | 11h 48m | 2 tasks | 9 files |
## Accumulated Context
@@ -303,6 +305,9 @@ Recent decisions affecting current work:
- [Phase 09]: Artist name_key and slug remain model-owned lifecycle fields and are not exposed by the admin writable projection
- [Phase 09]: The Phase 9 Genre tracer remains the one production controller; form capability was added without a parallel route or identity
- [Phase 09]: The tracer list and columns were already byte-equivalent to the tracked Winter source, so Task 2 added behavioral proof rather than rewriting them
- [Phase 09]: The tracked Style source declares no dropdown provider or filter, so production YAML stays exact while isolated compiler fixtures prove typed scalars and provider rejection
- [Phase 09]: Style slug retains the tracked update-only readonly schema and is generated on create by the model lifecycle
- [Phase 09]: Style equal-value list ordering is explicitly stabilized by the shared primary-key tie-breaker
### Pending Todos
@@ -325,6 +330,6 @@ Items acknowledged and carried forward from previous milestone close:
## Session Continuity
Last session: 2026-09-26T01:03:13.196Z
Stopped at: Completed 09-08-PLAN.md
Last session: 2026-09-26T13:09:59.379Z
Stopped at: Completed 09-09-PLAN.md
Resume file: None