docs(16.2): re-verify after gap closure 16.2-07 and UAT; phase complete
16.2-VERIFICATION.md passed 14/14: the five human items are resolved by the 16.2-07 gate log and the UAT re-run on v0.1.20 (16.2-UAT.md 5/5). covered_files adds 16.2-07 PLAN/SUMMARY and openapi_conformance_test.go; digest recomputed with verification.fingerprint. Re-verified by hand because msd-core 1.14.0 re-stales a report after gap closure and its verifier ignores passed UAT. STATE points at 16.3 (phase.complete picked 11, an executed phase that is only stale).
This commit is contained in:
@@ -1,19 +1,20 @@
|
||||
---
|
||||
msd_state_version: "1.0"
|
||||
milestone: v1.0
|
||||
current_phase: "16.2"
|
||||
current_phase_name: Plugin-provided field types and the Blog Editor formwidget (INSERTED)
|
||||
status: executing
|
||||
stopped_at: Completed 16.2-07-PLAN.md
|
||||
last_updated: "2026-10-10T19:05:40.959Z"
|
||||
current_phase: "16.3"
|
||||
current_phase_name: Backend admin personal API tokens with scopes
|
||||
status: planning
|
||||
stopped_at: "Phase 16.2 complete (re-verified after 16.2-07, UAT 5/5); Phase 16.3 ready to plan"
|
||||
last_updated: "2026-10-10T21:39:28.413Z"
|
||||
last_activity: 2026-10-10
|
||||
last_activity_desc: Phase 16.2 execution started
|
||||
state_head: aba063f723fbf629d1a2968dc1c8309926dc36fd
|
||||
last_activity_desc: Phase 16.2 complete, next Phase 16.3
|
||||
state_head: ed8210132ed77af6a5abdf65949357d4b5b14f8c
|
||||
progress:
|
||||
total_phases: 35
|
||||
completed_phases: 13
|
||||
total_plans: 158
|
||||
completed_plans: 154
|
||||
percent: 48
|
||||
gsd_state_version: "1.0"
|
||||
milestone_name: milestone
|
||||
---
|
||||
@@ -25,22 +26,22 @@ milestone_name: milestone
|
||||
See: .planning/PROJECT.md (updated 2026-09-16)
|
||||
|
||||
**Core value:** An existing WinterCMS-shaped app can be ported plugin by plugin to a single Go binary without its frontend noticing: the PHP version's API contract is the acceptance test.
|
||||
**Current focus:** Phase 16.2 — Plugin-provided field types and the Blog Editor formwidget (INSERTED)
|
||||
**Current focus:** Phase 16.3 — Backend admin personal API tokens with scopes
|
||||
|
||||
## Current Position
|
||||
|
||||
Phase: 16.2 (Plugin-provided field types and the Blog Editor formwidget (INSERTED)) — EXECUTING
|
||||
Plan: 2 of 7
|
||||
Status: Ready to execute
|
||||
Last activity: 2026-10-10 — Phase 16.2 execution started
|
||||
Phase: 16.3 (Backend admin personal API tokens with scopes) — READY TO PLAN
|
||||
Plan: Not started
|
||||
Status: Ready to plan
|
||||
Last activity: 2026-10-10 — Phase 16.2 complete, next Phase 16.3
|
||||
|
||||
Progress: [██████████] 100%
|
||||
Progress: [█████░░░░░] 48%
|
||||
|
||||
## Performance Metrics
|
||||
|
||||
**Velocity:**
|
||||
|
||||
- Total plans completed: 65
|
||||
- Total plans completed: 71
|
||||
- Average duration: 21 min
|
||||
- Total execution time: 104 min
|
||||
|
||||
@@ -59,6 +60,7 @@ Progress: [██████████] 100%
|
||||
| 10 | 5 | - | - |
|
||||
| 10.2 | 2 | - | - |
|
||||
| 14.1 | 2 | - | - |
|
||||
| 16.2 | 7 | - | - |
|
||||
|
||||
**Recent Trend:**
|
||||
|
||||
@@ -750,5 +752,5 @@ Items acknowledged and carried forward from previous milestone close:
|
||||
## Session Continuity
|
||||
|
||||
Last session: 2026-10-10T19:05:40.225Z
|
||||
Stopped at: Completed 16.2-07-PLAN.md
|
||||
Stopped at: Phase 16.2 complete, ready to plan Phase 11
|
||||
Resume file: None
|
||||
|
||||