docs(06): reopen phase after verification gaps
This commit is contained in:
@@ -8,10 +8,10 @@ last_updated: "2026-09-20T11:32:44.614Z"
|
||||
last_activity: 2026-09-20
|
||||
progress:
|
||||
total_phases: 15
|
||||
completed_phases: 6
|
||||
completed_phases: 5
|
||||
total_plans: 29
|
||||
completed_plans: 29
|
||||
percent: 40
|
||||
percent: 33
|
||||
---
|
||||
|
||||
# Project State
|
||||
@@ -27,7 +27,7 @@ See: .planning/PROJECT.md (updated 2026-09-16)
|
||||
|
||||
Phase: 06 (http-routing-auth-groups-and-rate-limiting) — EXECUTING
|
||||
Plan: 6 of 6
|
||||
Status: Ready to execute
|
||||
Status: Gaps found
|
||||
Last activity: 2026-09-20
|
||||
|
||||
Progress: [██████████] 100%
|
||||
@@ -36,7 +36,7 @@ Progress: [██████████] 100%
|
||||
|
||||
**Velocity:**
|
||||
|
||||
- Total plans completed: 28
|
||||
- Total plans completed: 29
|
||||
- Average duration: 21 min
|
||||
- Total execution time: 104 min
|
||||
|
||||
|
||||
Reference in New Issue
Block a user