docs(06): finalize gap-closure plan
This commit is contained in:
@@ -3,13 +3,13 @@ gsd_state_version: 1.0
|
||||
milestone: v1.0
|
||||
milestone_name: milestone
|
||||
status: executing
|
||||
stopped_at: Phase 6 verification found gaps
|
||||
last_updated: "2026-09-19T19:45:00Z"
|
||||
last_activity: 2026-09-19 -- Phase 6 verification gaps_found
|
||||
stopped_at: Completed 06-05-PLAN.md
|
||||
last_updated: "2026-09-19T22:19:43.824Z"
|
||||
last_activity: 2026-09-19 -- Phase 6 planning complete
|
||||
progress:
|
||||
total_phases: 15
|
||||
completed_phases: 5
|
||||
total_plans: 28
|
||||
total_plans: 29
|
||||
completed_plans: 28
|
||||
percent: 33
|
||||
---
|
||||
@@ -27,8 +27,8 @@ See: .planning/PROJECT.md (updated 2026-09-16)
|
||||
|
||||
Phase: 06 (http-routing-auth-groups-and-rate-limiting) — EXECUTING
|
||||
Plan: 5 of 5
|
||||
Status: Gaps found — throttle/InvScope order on live personal-token genres route
|
||||
Last activity: 2026-09-19
|
||||
Status: Ready to execute
|
||||
Last activity: 2026-09-19 -- Phase 6 planning complete
|
||||
|
||||
Progress: [██████████] 100%
|
||||
|
||||
|
||||
Reference in New Issue
Block a user