docs(14.2.1): create phase plan
This commit is contained in:
@@ -2,17 +2,17 @@
|
||||
gsd_state_version: "1.0"
|
||||
milestone: v1.0
|
||||
current_phase: 14.2.1
|
||||
current_phase_name: Translate plugin
|
||||
current_phase_name: translate-plugin
|
||||
status: verifying
|
||||
stopped_at: Completed 14.2.1-04-PLAN.md
|
||||
last_updated: "2026-10-06T12:21:36Z"
|
||||
last_updated: "2026-10-06T13:18:47.315Z"
|
||||
last_activity: 2026-10-06
|
||||
last_activity_desc: 14.2.1-04 tests, phase gate, and security review
|
||||
state_head: ba6e436
|
||||
state_head: 249b4d10cac25d64f987d719fdb581bb08c0aac0
|
||||
progress:
|
||||
total_phases: 26
|
||||
completed_phases: 12
|
||||
total_plans: 129
|
||||
total_plans: 131
|
||||
completed_plans: 129
|
||||
milestone_name: milestone
|
||||
---
|
||||
@@ -28,10 +28,10 @@ See: .planning/PROJECT.md (updated 2026-09-16)
|
||||
|
||||
## Current Position
|
||||
|
||||
Phase: 14.2.1 (Translate plugin) — VERIFYING
|
||||
Phase: 14.2.1 (translate-plugin) — READY TO EXECUTE
|
||||
Plan: 4 of 4 complete
|
||||
Status: Ready for phase verification / UAT
|
||||
Last activity: 2026-10-06 — End-to-end tests, matrices, fail-closed gate, security review
|
||||
Status: Verification gaps — CR-01 admin ML locale switch; do not mark complete
|
||||
Last activity: 2026-10-06 — 14.2.1-VERIFICATION.md status gaps_found (14/16)
|
||||
|
||||
Progress: [██████████] 100%
|
||||
|
||||
|
||||
Reference in New Issue
Block a user