3408742fb0
test(10): persist human verification items as UAT
2026-10-11 17:13:01 +02:00
f31ea9387f
docs(10): re-verify after go-stage fixes, phase 10 human_needed
2026-10-11 17:12:55 +02:00
fc7cfaf51c
docs(10): re-verify after quick-261011-mag, hygiene closed, gaps_found on --all go stage
2026-10-11 16:29:35 +02:00
d2fa195a91
docs(10): re-verify stale phase 10 report, gaps_found on check-phase10 hygiene gate
2026-10-11 15:54:52 +02:00
Jakub Zych
c05ad09dc2
docs(planning): commit accumulated workflow artifacts
2026-10-06 22:31:37 +02:00
Jakub Zych
3f650ffcd4
docs(10, 10.2): regenerate verification reports for modules/ paths
2026-10-01 23:32:42 +02:00
Jakub Zych
bbceeb957f
docs(10.1-04): record the Phase 10.1 security review and validation map
...
- 10.1-SECURITY-REVIEW.md: T-10.1-01 to T-10.1-22 and T-10.1-SC with
mitigation, test or gate stage, observed result and 23 removal checks
- 10.1-VALIDATION.md: every plan task mapped to its command, all green
under check-phase10.1.sh --all; nyquist_compliant and wave 0 complete
- Phase 10 deferred item for the parity failures marked resolved
2026-09-29 03:13:18 +02:00
Jakub Zych
35f55c733d
docs(10): re-verify phase after CR-01 fix
2026-09-27 20:45:11 +02:00
Jakub Zych
c7487f6799
docs(10): re-review CR-01 fix and record approved UAT
2026-09-27 20:38:18 +02:00
Jakub Zych
a405b1b7ff
docs(quick-260927-q23): fix CR-01: /auth/refresh must enforce tokens_valid_after and is_activated
2026-09-27 19:12:05 +02:00
Jakub Zych
815cb903c6
test(10): persist human verification items as UAT
2026-09-27 18:44:38 +02:00
Jakub Zych
f47a560cc8
docs(10): add phase verification report
2026-09-27 18:44:23 +02:00
Jakub Zych
6918ec5998
docs(10): add code review report and disposition
2026-09-27 18:36:06 +02:00
Jakub Zych
3bdf6c9301
docs(10-05): complete unit tests, assembled acceptance and phase gate plan
2026-09-27 18:23:44 +02:00
Jakub Zych
074fc52e5e
docs(10-05): Phase 10 security review and final validation map
...
- 10-SECURITY-REVIEW.md: T-10-01..T-10-25 and T-10-SC with mitigation,
test or gate stage, observed result, residual risk and the removal
(mutation) checks behind every high threat
- 10-VALIDATION.md: executed task commands, gate statuses, Wave 0 done,
nyquist_compliant after scripts/check-phase10.sh --all passed
2026-09-27 18:22:01 +02:00
Jakub Zych
8259a456bb
docs(10-04): complete relation manager and shell polish plan
2026-09-27 17:29:15 +02:00
Jakub Zych
1964844eb9
docs(10-03): complete admin lists, forms, filters and settings plan
2026-09-27 17:02:31 +02:00
Jakub Zych
453b8ae786
docs(10-02): complete admin backend contract plan
2026-09-27 16:30:15 +02:00
Jakub Zych
e9b48d4720
docs(10-01): complete admin SPA tracer plan
2026-09-27 15:37:02 +02:00
Jakub Zych
8c3e131111
docs(10): create phase plan
2026-09-27 14:11:07 +02:00
Jakub Zych
42c7216f5f
docs(10): record plan-time decisions and plan count
2026-09-27 13:26:11 +02:00
Jakub Zych
ec97007637
docs(10): research admin Vue SPA phase
2026-09-27 13:23:46 +02:00
Jakub Zych
2efe51a168
docs(10): capture phase context
2026-09-26 23:21:43 +02:00