--- gsd_state_version: 1.0 milestone: v1.0 milestone_name: milestone status: executing stopped_at: Phase 2 context gathered last_updated: "2026-09-16T10:53:48.889Z" last_activity: 2026-09-16 -- Phase 01 execution started progress: total_phases: 15 completed_phases: 0 total_plans: 4 completed_plans: 0 percent: 0 --- # Project State ## Project Reference See: .planning/PROJECT.md (updated 2026-09-16) **Core value:** An existing WinterCMS-shaped app can be ported plugin by plugin to a single Go binary without its frontend noticing: the PHP version's API contract is the acceptance test. **Current focus:** Phase 01 — framework-kernel-foundation ## Current Position Phase: 01 (framework-kernel-foundation) — EXECUTING Plan: 1 of 4 Status: Executing Phase 01 Last activity: 2026-09-16 -- Phase 01 execution started Progress: [░░░░░░░░░░] 0% ## Performance Metrics **Velocity:** - Total plans completed: 0 - Average duration: - - Total execution time: 0 hours **By Phase:** | Phase | Plans | Total | Avg/Plan | |-------|-------|-------|----------| | - | - | - | - | **Recent Trend:** - Last 5 plans: - - Trend: - *Updated after each plan completion* ## Accumulated Context ### Roadmap Evolution - Phase 2 edited: edited fields: depends_on (Phase 1), goal (summer parity:* on bonfire, no longer a parallel workstream) ### Decisions Decisions are logged in PROJECT.md Key Decisions table. Recent decisions affecting current work: - Roadmap: gormigrate (not goose) is the migration tool, per STACK.md's more recent reasoning — ARCHITECTURE.md/PITFALLS.md text still says goose in places; treat gormigrate as authoritative when phases 3 and 5 are planned. - Roadmap: two repos from day one — `summercms.go` (framework, no app knowledge) and `fonoteka.go` (sibling app repo, go.work workspace of plugins). Every phase states which repo(s) it writes to. - Roadmap: the parity harness (Phase 2) and the first vertical slice (Phase 3) are sequenced immediately after kernel foundation, ahead of any further kernel broadening, to avoid the documented Scala-era bottom-up-kernel failure mode. ### Pending Todos None yet. ### Blockers/Concerns - Phase 8 (OAuth2.1) needs a pre-planning check of `wavepath.org/plugins/golem15/oauthserver` to resolve whether `ClientCredentialsStorage`/`TokenExchangeStorage` are needed — flagged in research/SUMMARY.md Gaps, unresolved. - Phase 9 (admin schema pipeline / relation manager) is the least-precedented design surface in the research — plan with `--research-phase`. - Phase 11 (River dual-driver split) is documented but unverified against a real build — plan with `--research-phase` and budget a timed-latency test. ## Deferred Items Items acknowledged and carried forward from previous milestone close: | Category | Item | Status | Deferred At | |----------|------|--------|-------------| | *(none — first milestone)* | | | | ## Session Continuity Last session: 2026-09-16T10:47:33.084Z Stopped at: Phase 2 context gathered Resume file: .planning/phases/02-api-parity-harness-bootstrap/02-CONTEXT.md