Files
summercms/.planning/STATE.md
2026-09-16 09:36:57 +02:00

2.8 KiB

Project State

Project Reference

See: .planning/PROJECT.md (updated 2026-09-16)

Core value: An existing WinterCMS-shaped app can be ported plugin by plugin to a single Go binary without its frontend noticing: the PHP version's API contract is the acceptance test. Current focus: Phase 1 — Framework kernel foundation (parallel: Phase 2 — API parity harness bootstrap)

Current Position

Phase: 1 of 15 (Framework kernel foundation) Plan: TBD (roadmap just created, plans not yet written) Status: Ready to plan Last activity: 2026-09-16 — ROADMAP.md and STATE.md created from PROJECT.md, REQUIREMENTS.md and research/{SUMMARY,ARCHITECTURE,PITFALLS}.md

Progress: [░░░░░░░░░░] 0%

Performance Metrics

Velocity:

  • Total plans completed: 0
  • Average duration: -
  • Total execution time: 0 hours

By Phase:

Phase Plans Total Avg/Plan
- - - -

Recent Trend:

  • Last 5 plans: -
  • Trend: -

Updated after each plan completion

Accumulated Context

Decisions

Decisions are logged in PROJECT.md Key Decisions table. Recent decisions affecting current work:

  • Roadmap: gormigrate (not goose) is the migration tool, per STACK.md's more recent reasoning — ARCHITECTURE.md/PITFALLS.md text still says goose in places; treat gormigrate as authoritative when phases 3 and 5 are planned.
  • Roadmap: two repos from day one — summercms.go (framework, no app knowledge) and fonoteka.go (sibling app repo, go.work workspace of plugins). Every phase states which repo(s) it writes to.
  • Roadmap: the parity harness (Phase 2) and the first vertical slice (Phase 3) are sequenced immediately after kernel foundation, ahead of any further kernel broadening, to avoid the documented Scala-era bottom-up-kernel failure mode.

Pending Todos

None yet.

Blockers/Concerns

  • Phase 8 (OAuth2.1) needs a pre-planning check of wavepath.org/plugins/golem15/oauthserver to resolve whether ClientCredentialsStorage/TokenExchangeStorage are needed — flagged in research/SUMMARY.md Gaps, unresolved.
  • Phase 9 (admin schema pipeline / relation manager) is the least-precedented design surface in the research — plan with --research-phase.
  • Phase 11 (River dual-driver split) is documented but unverified against a real build — plan with --research-phase and budget a timed-latency test.

Deferred Items

Items acknowledged and carried forward from previous milestone close:

Category Item Status Deferred At
(none — first milestone)

Session Continuity

Last session: 2026-09-16 Stopped at: Roadmap and state files written; awaiting user approval of ROADMAP.md before proceeding to /gsd:plan-phase 1. Resume file: None