* docs(#2629): adr — phase effort estimation & calibration design lock * docs(#2629): annotate phase-0 status and link adr cross-reference * docs(#2629): derive estimate confidence from sample count, not self-rating
This commit is contained in:
119
docs/adr/2629-phase-effort-estimation-calibration.md
Normal file
119
docs/adr/2629-phase-effort-estimation-calibration.md
Normal file
@@ -0,0 +1,119 @@
|
||||
# Phase effort is estimated against a calibrated smart-zone budget, not a static heuristic
|
||||
|
||||
- **Status:** Accepted (Phase 0 — ADR only; locks the contract Phases 1–3 execute against. No production code lands in this PR.)
|
||||
- **Date:** 2026-07-24
|
||||
- **Issue:** #2629
|
||||
- **Epic:** #1952 (Phase 0 design lock; epic stays open until Phase 3 merges)
|
||||
- **Implementation:** Phase 1 #2630 (module + config), Phase 2 #2631 (planner emits), Phase 3 #2632 (actuals + calibration loop)
|
||||
|
||||
## Context
|
||||
|
||||
GSD sizes a phase with a static prose heuristic and never checks it against reality. `agents/gsd-planner.md` `<scope_estimation>` maps a phase to Light/Medium/Heavy and targets "~50% context budget, 2-3 tasks"; `agents/gsd-plan-checker.md` Dimension 5 pass/fails on it. No figure is recorded in the plan, no actuals are captured, and nothing calibrates the heuristic against what phases actually cost. The developer learns a phase was oversized only when the executor runs long and output quality degrades.
|
||||
|
||||
That matters more for an LLM executor than it did for humans, because degradation begins well before the advertised context window is full.
|
||||
|
||||
## Decision
|
||||
|
||||
### 1. `estimate` — additive, optional PLAN.md frontmatter
|
||||
|
||||
```yaml
|
||||
estimate:
|
||||
tokens: 60000 # integer > 0 — projected execution cost
|
||||
tasks: 5 # integer > 0 — task count the projection assumes
|
||||
confidence: med # low | med | high — DERIVED, not self-rated (see below)
|
||||
```
|
||||
|
||||
Optional. A PLAN.md without `estimate` behaves exactly as today.
|
||||
|
||||
**`confidence` is derived from calibration sample count, not from the planner's self-assessment.** It is a pure function of how much measured history backs the number:
|
||||
|
||||
| Calibration samples (`n`) | `confidence` |
|
||||
|---|---|
|
||||
| `n < 3` (no correction applied) | `low` |
|
||||
| `3 <= n < 6` | `med` |
|
||||
| `n >= 6` | `high` |
|
||||
|
||||
This is deliberate and it is the one place this ADR overrules the obvious design. Asking the planner to rate its own certainty is endogenous self-assessment, and this project has **measured** that mechanism and found it weak: `gsd-core/references/honest-verifier.md:25-29` records that "abstain if unsure" moves a confident-false-pass rate only 100% → 67%, "and only on ambiguity it already notices; on a true blind spot it stays confidently wrong." `honest-verifier.md` therefore routes on an exogenous tag and contains no "are you sure?" prompt, and `.out-of-scope/general-purpose-agent-prompt-skills.md` (#2614) declines core mechanisms centered on self-rated confidence on exactly that evidence.
|
||||
|
||||
Deriving `confidence` from `n` keeps the field exogenous and reproducible: two planners looking at the same project must produce the same value, and the field answers the question a reader actually has — *how much measured history is behind this figure?* — rather than how certain the model happens to feel.
|
||||
|
||||
### 2. `actuals` — additive, optional SUMMARY.md frontmatter, measured on the *same scale*
|
||||
|
||||
```yaml
|
||||
actuals:
|
||||
tokens: 74000 # estimateTokens() over the realized diff
|
||||
tasks: 5
|
||||
commits: 7
|
||||
```
|
||||
|
||||
**`actuals.tokens` is not harness-reported token usage.** An executor subagent cannot read its own consumption — real counts exist only in the Claude Code statusline hook input (`hooks/gsd-statusline.js:314`, `context_window.current_usage`), which is not available to a spawned agent. Actuals are therefore measured with the **same `estimateTokens()` function** (`src/prompt-budget.cts:87`) applied to the realized diff.
|
||||
|
||||
This is a deliberate choice, not a workaround. The calibration ratio is only meaningful if numerator and denominator share a scale; pairing a chars/4 estimate with a harness-reported actual would measure the gap between two *measurement methods*, not the gap between projection and reality.
|
||||
|
||||
### 3. The smart-zone budget is a policy default, not a benchmark constant
|
||||
|
||||
New config key `workflow.smart_zone_tokens`, default `100000`, positive integer.
|
||||
|
||||
The literature cited on #1952 converges on the qualitative claim — degradation starts before the advertised ceiling, is non-uniform, and worsens as advertised windows grow — but **none of it yields a universal number**:
|
||||
|
||||
- Liu et al., *Lost in the Middle* (arXiv:2307.03172) — U-shaped positional degradation.
|
||||
- Chroma Research, *Context Rot* (2025) — a "200K window" model can degrade significantly at 50K.
|
||||
- Modarressi et al., *NoLiMa* (arXiv:2502.05167) — GPT-4o falls from 99.3% to 69.7% at 32K on latent association.
|
||||
- Hsieh et al., *RULER* (arXiv:2404.06654) — only half of models claiming ≥32K hold up at 32K.
|
||||
|
||||
The effective ceiling is model-, task-, and distractor-dependent. **100k is a conservative operating policy that the calibration loop is expected to correct per project.** Anyone reading this later: do not cite 100000 as a measured constant, and do not "fix" it by pointing at a benchmark. It is configurable precisely because it will drift as models change.
|
||||
|
||||
### 4. Calibration: median ratio, clamped, with a minimum sample count
|
||||
|
||||
```
|
||||
ratio_i = actuals_i.tokens / estimate_i.tokens (phases with BOTH fields)
|
||||
factor = clamp(median(ratio_i), 0.5, 3.0) when n >= 3
|
||||
factor = 1.0 when n < 3
|
||||
```
|
||||
|
||||
- **Median, not mean** — one pathological phase (an aborted run, a mass rename) must not swing the projection for every later phase.
|
||||
- **Clamped to [0.5, 3.0]** — bounds the blast radius of a degenerate history; a factor outside that range indicates the estimator is wrong in kind, not in degree, and should be fixed rather than amplified.
|
||||
- **`n >= 3` before any correction applies** — below that, the sample says more about variance than about bias.
|
||||
|
||||
Persisted to `.planning/estimation-calibration.json` with a `schema_version` field, written by `extract-learnings`, read at plan time. Versioned from the first write so the schema can migrate without a silent misread.
|
||||
|
||||
### 5. The over-budget flag is advisory, never a block
|
||||
|
||||
An estimate exceeding the budget produces a warning plus a split recommendation. It does not fail planning, does not block execution, and does not gate a PR. GSD advises on phase size; it does not overrule the developer on it.
|
||||
|
||||
### 6. Calibration lives in `extract-learnings`, not `gsd-verifier`
|
||||
|
||||
#1952 proposed "`gsd-verifier.md` or `extract-learnings`". The choice is forced: `tests/agent-size-budget.test.cjs` caps LARGE-tier agents at 49,152 bytes and `agents/gsd-verifier.md` is 49,140 — **12 bytes of headroom.** `gsd-core/workflows/extract-learnings.md` is 12,893 bytes against a 40,960 DEFAULT cap, and already reads every `*-SUMMARY.md` for the phase.
|
||||
|
||||
Recorded because the reasoning is invisible from the code: a future contributor asking "why isn't this in the verifier, next to the other phase-completion analysis?" will otherwise re-litigate it and hit the cap.
|
||||
|
||||
## Rationale
|
||||
|
||||
- **Additive-optional keeps Hyrum's Law in check.** Both new blocks are optional, so every existing PLAN.md and SUMMARY.md, and every consumer that reads them, is unaffected. No migration.
|
||||
- **Gall's Law.** This grows the existing working system — the Context Weight heuristic — into a recorded figure, then into a calibrated one. It does not replace phase sizing with a new engine.
|
||||
- **The estimate is the quantitative backbone under tracer-first planning (#1945).** Tracer bullets say *slice thin*; the estimate says *here is the measured reason this phase must be sliced, and how big the slices should be for this codebase*.
|
||||
- **Estimation without calibration is the failure mode being fixed, not a smaller version of it.** Hunt & Thomas's discipline is to log the estimate, track it against the actual, and investigate a wide miss. A fixed heuristic that never learns stays wrong in the same direction forever — which is the status quo.
|
||||
- **Every signal in this design is exogenous.** The correction routes on a measured ratio; `confidence` routes on a sample count. Nothing routes on the model's self-assessment. This is the same property `honest-verifier.md` names "exogenous, not endogenous", applied to estimation — and it is what places this work inside the carve-out in `.out-of-scope/general-purpose-agent-prompt-skills.md`, which denies *self-rated* confidence mechanisms while explicitly excepting "objectively-measured or externally-triggered calibration… a categorically different mechanism."
|
||||
|
||||
## Consequences
|
||||
|
||||
- PLAN.md and SUMMARY.md each gain one optional frontmatter block; `docs/reference/plan-md.md` gains an `estimate` row.
|
||||
- One new config key, and one new pure module (`src/phase-estimation.cts`) that imports `estimateTokens` from `prompt-budget.cts` rather than copying it — no duplicated constant to drift.
|
||||
- The estimator and the default budget must be revisited as models change. Mitigated by making the budget configuration and the correction self-calibrating.
|
||||
- Calibration is inert on a project's first two phases (`n < 3`). This is intended: a correction derived from one or two samples is noise wearing a decimal point.
|
||||
- Phases 1 and 2 each merge with a surface the next phase consumes. Phase 1's module is deliberately unconsumed at merge; Phase 2 emits an uncalibrated estimate. The loop is only closed by Phase 3, and **the epic does not close before it is.**
|
||||
|
||||
## Revisit if
|
||||
|
||||
- A runtime makes real per-agent token accounting available to a spawned subagent. Decision 2's same-scale rule should then be re-examined — though note that switching `actuals` to a different scale invalidates the accumulated calibration history, so the migration must reset `.planning/estimation-calibration.json`, not reinterpret it.
|
||||
- The clamp in Decision 4 is hit routinely in practice. That is evidence the estimator is systematically wrong rather than noisy, and the fix belongs in the estimator, not in a wider clamp.
|
||||
|
||||
## References
|
||||
|
||||
- `gsd-core/references/context-budget.md` — existing context-degradation tiers and the `context_window` / `workflow.context_guard_mode` keys this sits beside.
|
||||
- `src/prompt-budget.cts:87` — `estimateTokens`, the shared measurement primitive.
|
||||
- `tests/agent-size-budget.test.cjs` — the tier caps that force Decision 6.
|
||||
- `gsd-core/references/honest-verifier.md:25-29` — the measured result that self-rated confidence is weak, and the exogenous-not-endogenous property Decision 1 inherits.
|
||||
- `.out-of-scope/general-purpose-agent-prompt-skills.md` (#2614) — denies self-rated-confidence mechanisms in core; its "What this does NOT cover" section excepts externally-measured calibration, which is what this ADR specifies.
|
||||
- [ADR-2164](2164-statusline-scope-boundary.md) — prior art for a scope-boundary policy ADR.
|
||||
- Issues: #1952 (epic), #1945 (tracer-first), #2630 / #2631 / #2632 (implementation phases).
|
||||
@@ -116,7 +116,7 @@ This replaces a hand-maintained table that had drifted to **40 of 65 ADRs** —
|
||||
|
||||
<!-- ADR-INDEX:START — generated by scripts/gen-adr-index.cjs; do not edit by hand -->
|
||||
|
||||
### Active decisions (50)
|
||||
### Active decisions (51)
|
||||
|
||||
These govern the system as it stands. Cite these.
|
||||
|
||||
@@ -171,6 +171,7 @@ These govern the system as it stands. Cite these.
|
||||
| [ADR-2164](2164-statusline-scope-boundary.md) | Statusline draws its data boundary at local, read-only sources | Accepted | — |
|
||||
| [ADR-2207](2207-status-field-lifecycle-ownership.md) | STATE.md `Status` lifecycle — phase-completion writes an intermediate state; milestone-close owns termination | Accepted | — |
|
||||
| [ADR-2346](2346-command-dispatch-completion.md) | Command Dispatch Completion | Accepted | — |
|
||||
| [ADR-2629](2629-phase-effort-estimation-calibration.md) | Phase effort is estimated against a calibrated smart-zone budget, not a static heuristic | Accepted | — |
|
||||
| [ADR-3660](3660-runtime-artifact-layout-module.md) | Runtime Artifact Layout Module owns per-runtime artifact placement | Accepted | [ADR-1239](1239-gsd-embeddable-orchestration-engine.md) |
|
||||
|
||||
### Proposed (9)
|
||||
@@ -203,7 +204,7 @@ Historical record. **Do not follow these** — each names what replaced it, or w
|
||||
| [ADR-0012](0012-command-routing-hub.md) | CommandRoutingHub as single dispatch seam for CJS command families | Superseded | [ADR-0174](0174-retire-gsd-sdk-package-boundary.md) |
|
||||
| [ADR-3524](3524-cjs-sdk-hard-seam.md) | CJS↔SDK hard seam — one source of truth per Shared Module | Superseded | [ADR-0174](0174-retire-gsd-sdk-package-boundary.md) |
|
||||
|
||||
_66 ADRs. Generated by `scripts/gen-adr-index.cjs` — run `--write` after adding or restatusing an ADR._
|
||||
_67 ADRs. Generated by `scripts/gen-adr-index.cjs` — run `--write` after adding or restatusing an ADR._
|
||||
|
||||
<!-- ADR-INDEX:END -->
|
||||
|
||||
|
||||