* test(#2522): wrapped + blank-line success-criteria parse * fix(#2522): fold wrapped success-criteria lines into their criterion * chore(#2522): backfill changeset pr to 2637
6 lines
602 B
Markdown
6 lines
602 B
Markdown
---
|
|
type: Fixed
|
|
pr: 2637
|
|
---
|
|
**`roadmap get-phase` no longer drops success criteria that wrap onto a second line** — the parser broke the criteria run at any indented continuation line, truncating the wrapped criterion (losing its trailing `[REQ-ID]` tag) and silently dropping every criterion below it. `verify-work` and `plan-phase` consumed the shortened list, so a phase could be planned and certified complete against a strict subset of its own success criteria with nothing reporting the gap. Continuation lines now fold into their criterion; blank-line-separated criteria still parse. (#2522)
|