Files
summercms-initial-research/.planning/STATE.md
2026-02-05 13:08:42 +01:00

2.8 KiB

Project State

Project Reference

See: .planning/PROJECT.md (updated 2026-02-04)

Core value: A CMF that enables rapid application development with the flexibility to support any use case, delivered with the performance and horizontal scaling that PHP cannot provide. Current focus: Phase 2 - Plugin System (next)

Current Position

Phase: 2 of 10 (Plugin System) Plan: 0 of 3 in current phase Status: Ready to plan Last activity: 2026-02-05 - Completed quick task 001: Update JDK requirement to 21+ for Loom virtual threads

Progress: [###.......] 10% (3/29 plans)

Performance Metrics

Velocity:

  • Total plans completed: 3
  • Average duration: 123 min
  • Total execution time: 6.15 hours

By Phase:

Phase Plans Total Avg/Plan
01 3 329min 110min

Recent Trend:

  • Last 5 plans: 01-01 (39min), 01-02 (35min), 01-03 (255min)
  • Trend: 01-03 was longer due to Besom API debugging

Updated after each plan completion

Accumulated Context

Decisions

Decisions are logged in PROJECT.md Key Decisions table. Recent decisions affecting current work:

  • [Roadmap]: Comprehensive depth selected (10 phases, 29 plans)
  • [Roadmap]: Plugin System identified as architectural bottleneck - Phase 2
  • [Research]: Quill for database (compile-time SQL validation), ScalaTags + HTMX for frontend
  • [01-01]: Mill 1.1.1 required for Java 25 compatibility (ASM class file version 69)
  • [01-01]: Use root.config import to avoid zio.config shadowing
  • [01-02]: Use 'hikari' prefix for HikariCP config to avoid conflict with ZIO config 'database' prefix
  • [01-02]: Migrations run via CLI only, not auto-run on startup
  • [01-03]: Besom 0.5.0 used for Pulumi (0.4.0 had breaking Config API)
  • [01-03]: Repository refineOrDie before flatMap to avoid union type errors
  • [01-03]: Infra uses Scala CLI, not Mill (Besom requirement)

Pending Todos

None yet.

Blockers/Concerns

  • Research flag: Plugin System (Phase 2) needs deep research before planning
  • Research flag: Admin Backend (Phase 7-8) has hidden complexity (YAML edge cases)

Quick Tasks Completed

# Description Date Commit Directory
001 Update JDK requirement to 21+ for Loom virtual threads 2026-02-05 64dcded 001-update-jdk-requirement-to-21-for-loom-vi

Session Continuity

Last session: 2026-02-05 Stopped at: Completed 01-03-PLAN.md (Repository Pattern and Infrastructure) Resume file: None

Phase 1 Foundation - Complete

All 3 plans completed:

  • 01-01: Mill build, ZIO HTTP server, health endpoint
  • 01-02: Quill PostgreSQL context, Flyway migrations
  • 01-03: Repository pattern, Besom infrastructure, Dockerfile

Ready for Phase 2: Plugin System