@@ -1454,7 +1454,7 @@ Plans:
3. `tools/list` lists only the tools the session's principals may call (frontend permissions through the merged group/user permissions, backend permissions and token scope through cabana), and a call runs through the route's own middleware.
4. An editor signs in once through `wristband` OAuth as a frontend user; with a verified link to a backend user, backend-guarded tools such as Journal's run as that admin, and removing the link or the grant removes them. The phase gets a security review; the MCP SDK dependency has a decision note before code lands; unit tests are the last plan.
**Plans:** 4/5 plans executed
**Plans:** 5/5 plans executed
Plans:
**Wave 1**
@@ -1470,7 +1470,7 @@ Plans:
- [x] 19.7-04-PLAN.md — sm-oauthserver-plugin `backend` scope, `oas_at_` verifier and MCP consent JSON; Journal tools; vue-demo-app `/connect` and `/link-admin`; sm-demo-app wiring, e2e and deploy notes; plugin releases
**Wave 5** *(blocked on Wave 4 completion)*
- [ ] 19.7-05-PLAN.md — Unit tests across six repos, `scripts/check-phase19.7.sh`, the filled validation map and the security review
- [x] 19.7-05-PLAN.md — Unit tests across six repos, `scripts/check-phase19.7.sh`, the filled validation map and the security review
### Phase 19.8: Console commands overhaul (INSERTED)
@@ -1607,7 +1607,7 @@ Phases execute in numeric order: 1 → 2 → 3 → 4 → 5 → 6 → 7 → 8 →
| 19.5. Social login in sm-user-plugin | 5/5 | Complete | 2026-10-21 |
| 19.6. Two-factor auth and device flow in sm-user-plugin | 0/TBD | Not started | - |
| 19.6.1. Backend Administrators screen (INSERTED) | 5/5 | Complete | 2026-10-22 |
| 19.7. Generic MCP module | 4/5 | In Progress| |
| 19.7. Generic MCP module | 5/5 | In Progress| |
| 19.8. Console commands overhaul (INSERTED) | 6/6 | In Progress| |
| 20. Demo instance with every shared plugin | 0/TBD | Not started | - |
| 30. Płytarium cutover | 0/TBD | Not started | - |

View File

@@ -4,11 +4,11 @@ milestone: v1.0
current_phase: "19.7"
current_phase_name: Generic MCP module (INSERTED)
status: executing
stopped_at: Completed 19.7-04-PLAN.md
last_updated: "2026-10-23T11:18:15.153Z"
stopped_at: Completed 19.7-05-PLAN.md
last_updated: "2026-10-23T12:42:11.559Z"
last_activity: 2026-10-23
last_activity_desc: "Completed 19.7-04: oauthserver v0.1.2, Journal v0.2.3, demo MCP wiring"
state_head: 81266de77d84180e1158f477d9d6f3467f231303
last_activity_desc: "Completed 19.7-05: unit tests, check-phase19.7.sh gate, security review; phase verification next"
state_head: d9d2acae8876af174429581d1ff582cccf2d0b38
progress:
total_phases: 45
completed_phases: 37
@@ -1068,5 +1068,5 @@ Items acknowledged and carried forward from previous milestone close:
## Session Continuity
Last session: 2026-10-22T22:22:57.128Z
Stopped at: Completed 19.7-04-PLAN.md
Stopped at: Completed 19.7-05-PLAN.md