docs(phase-06): mark progress table as gaps found

This commit is contained in:
Jakub Zych
2026-09-19 21:44:36 +02:00
parent 59d9a26aad
commit cb34de4203

View File

@@ -410,7 +410,7 @@ Phases execute in numeric order: 1 → 2 → 3 → 4 → 5 → 6 → 7 → 8 →
| 3. First vertical slice — genres end to end | 4/4 | Complete | 2026-09-17 |
| 4. CLI scaffolding, i18n and mail | 4/4 | Complete | 2026-09-18 |
| 5. Data layer full fidelity | 6/6 | Complete | 2026-09-18 |
| 6. HTTP routing, auth groups and rate limiting | 5/5 | Complete | 2026-09-19 |
| 6. HTTP routing, auth groups and rate limiting | 5/5 | Gaps found | - |
| 7. User plugin and authentication | 0/TBD | Not started | - |
| 8. OAuth2.1 authorization server | 0/TBD | Not started | - |
| 9. Backend admin authentication and schema pipeline | 0/TBD | Not started | - |