docs: create roadmap (15 phases)
This commit is contained in:
71
.planning/STATE.md
Normal file
71
.planning/STATE.md
Normal file
@@ -0,0 +1,71 @@
|
||||
# Project State
|
||||
|
||||
## Project Reference
|
||||
|
||||
See: .planning/PROJECT.md (updated 2026-09-16)
|
||||
|
||||
**Core value:** An existing WinterCMS-shaped app can be ported plugin by plugin to a single Go binary without its frontend noticing: the PHP version's API contract is the acceptance test.
|
||||
**Current focus:** Phase 1 — Framework kernel foundation (parallel: Phase 2 — API parity harness bootstrap)
|
||||
|
||||
## Current Position
|
||||
|
||||
Phase: 1 of 15 (Framework kernel foundation)
|
||||
Plan: TBD (roadmap just created, plans not yet written)
|
||||
Status: Ready to plan
|
||||
Last activity: 2026-09-16 — ROADMAP.md and STATE.md created from PROJECT.md, REQUIREMENTS.md and research/{SUMMARY,ARCHITECTURE,PITFALLS}.md
|
||||
|
||||
Progress: [░░░░░░░░░░] 0%
|
||||
|
||||
## Performance Metrics
|
||||
|
||||
**Velocity:**
|
||||
- Total plans completed: 0
|
||||
- Average duration: -
|
||||
- Total execution time: 0 hours
|
||||
|
||||
**By Phase:**
|
||||
|
||||
| Phase | Plans | Total | Avg/Plan |
|
||||
|-------|-------|-------|----------|
|
||||
| - | - | - | - |
|
||||
|
||||
**Recent Trend:**
|
||||
- Last 5 plans: -
|
||||
- Trend: -
|
||||
|
||||
*Updated after each plan completion*
|
||||
|
||||
## Accumulated Context
|
||||
|
||||
### Decisions
|
||||
|
||||
Decisions are logged in PROJECT.md Key Decisions table.
|
||||
Recent decisions affecting current work:
|
||||
|
||||
- Roadmap: gormigrate (not goose) is the migration tool, per STACK.md's more recent reasoning — ARCHITECTURE.md/PITFALLS.md text still says goose in places; treat gormigrate as authoritative when phases 3 and 5 are planned.
|
||||
- Roadmap: two repos from day one — `summercms.go` (framework, no app knowledge) and `fonoteka.go` (sibling app repo, go.work workspace of plugins). Every phase states which repo(s) it writes to.
|
||||
- Roadmap: the parity harness (Phase 2) and the first vertical slice (Phase 3) are sequenced immediately after kernel foundation, ahead of any further kernel broadening, to avoid the documented Scala-era bottom-up-kernel failure mode.
|
||||
|
||||
### Pending Todos
|
||||
|
||||
None yet.
|
||||
|
||||
### Blockers/Concerns
|
||||
|
||||
- Phase 8 (OAuth2.1) needs a pre-planning check of `wavepath.org/plugins/golem15/oauthserver` to resolve whether `ClientCredentialsStorage`/`TokenExchangeStorage` are needed — flagged in research/SUMMARY.md Gaps, unresolved.
|
||||
- Phase 9 (admin schema pipeline / relation manager) is the least-precedented design surface in the research — plan with `--research-phase`.
|
||||
- Phase 11 (River dual-driver split) is documented but unverified against a real build — plan with `--research-phase` and budget a timed-latency test.
|
||||
|
||||
## Deferred Items
|
||||
|
||||
Items acknowledged and carried forward from previous milestone close:
|
||||
|
||||
| Category | Item | Status | Deferred At |
|
||||
|----------|------|--------|-------------|
|
||||
| *(none — first milestone)* | | | |
|
||||
|
||||
## Session Continuity
|
||||
|
||||
Last session: 2026-09-16
|
||||
Stopped at: Roadmap and state files written; awaiting user approval of ROADMAP.md before proceeding to `/gsd:plan-phase 1`.
|
||||
Resume file: None
|
||||
Reference in New Issue
Block a user