docs(state): record 04-01 completion and advance to plan 02
Mark CLI-02 complete, log scaffolding registry and leaf-check decisions, and move Phase 4 progress to 1/4 plans. Co-authored-by: Cursor <cursoragent@cursor.com>
This commit is contained in:
@@ -22,7 +22,7 @@ Requirements for v1 (the Płytarium port). Each maps to roadmap phases. "User" b
|
||||
### Console and scaffolding (CLI)
|
||||
|
||||
- [x] **CLI-01**: The `summer` binary (cobra) discovers commands registered by plugins and offers rich output (spinner, progress bar, table, prompts) with non-TTY degradation, following the summer-bonfire design
|
||||
- [ ] **CLI-02**: Scaffolding commands generate a plugin, model, migration, command, job and admin controller with stubs that compile
|
||||
- [x] **CLI-02**: Scaffolding commands generate a plugin, model, migration, command, job and admin controller with stubs that compile
|
||||
- [ ] **CLI-03**: Migration commands run up, status, and roll back the last migration of a named plugin
|
||||
- [ ] **CLI-04**: Plugins register recurring commands (daily or interval) that a scheduler runs in-process or via `summer schedule:run`
|
||||
- [ ] **CLI-05**: Płytarium commands are ported: oauth-client (create, list without reprinting secrets, add redirect URIs, set scope ceiling), prune-notifications, reindex with drop-old-index flag
|
||||
@@ -164,7 +164,7 @@ Which phases cover which requirements. Updated during roadmap creation.
|
||||
| KERN-08 | Phase 1 | Complete |
|
||||
| KERN-09 | Phase 1 | Complete |
|
||||
| CLI-01 | Phase 1 | Complete |
|
||||
| CLI-02 | Phase 4 | Pending |
|
||||
| CLI-02 | Phase 4 | Complete |
|
||||
| CLI-03 | Phase 5 | Pending |
|
||||
| CLI-04 | Phase 11 | Pending |
|
||||
| CLI-05 | Phase 14 | Pending |
|
||||
|
||||
@@ -155,7 +155,7 @@ Plans:
|
||||
|
||||
**Wave 1**
|
||||
|
||||
- [ ] 04-01-PLAN.md — Generate compiling plugin artifacts, registry and model import checks
|
||||
- [x] 04-01-PLAN.md — Generate compiling plugin artifacts, registry and model import checks
|
||||
|
||||
**Wave 2** *(blocked on Wave 1 completion)*
|
||||
|
||||
@@ -367,7 +367,7 @@ Phases execute in numeric order: 1 → 2 → 3 → 4 → 5 → 6 → 7 → 8 →
|
||||
| 1. Framework kernel foundation | 4/4 | Complete | 2026-09-16 |
|
||||
| 2. API parity harness bootstrap | 5/5 | Complete | 2026-09-17 |
|
||||
| 3. First vertical slice — genres end to end | 4/4 | Complete | 2026-09-17 |
|
||||
| 4. CLI scaffolding, i18n and mail | 0/TBD | Not started | - |
|
||||
| 4. CLI scaffolding, i18n and mail | 1/4 | In Progress| |
|
||||
| 5. Data layer full fidelity | 0/TBD | Not started | - |
|
||||
| 6. HTTP routing, auth groups and rate limiting | 0/TBD | Not started | - |
|
||||
| 7. User plugin and authentication | 0/TBD | Not started | - |
|
||||
|
||||
@@ -3,14 +3,14 @@ gsd_state_version: 1.0
|
||||
milestone: v1.0
|
||||
milestone_name: milestone
|
||||
status: executing
|
||||
stopped_at: Phase 4 context gathered
|
||||
last_updated: "2026-09-18T11:24:07.910Z"
|
||||
last_activity: 2026-09-18 -- Phase 4 planning complete
|
||||
stopped_at: Completed 04-01-PLAN.md
|
||||
last_updated: "2026-09-18T11:42:23.658Z"
|
||||
last_activity: 2026-09-18
|
||||
progress:
|
||||
total_phases: 15
|
||||
completed_phases: 3
|
||||
total_plans: 17
|
||||
completed_plans: 13
|
||||
completed_plans: 14
|
||||
percent: 20
|
||||
---
|
||||
|
||||
@@ -21,16 +21,16 @@ progress:
|
||||
See: .planning/PROJECT.md (updated 2026-09-16)
|
||||
|
||||
**Core value:** An existing WinterCMS-shaped app can be ported plugin by plugin to a single Go binary without its frontend noticing: the PHP version's API contract is the acceptance test.
|
||||
**Current focus:** Phase 4 — cli scaffolding, i18n and mail
|
||||
**Current focus:** Phase 04 — cli-scaffolding-i18n-and-mail
|
||||
|
||||
## Current Position
|
||||
|
||||
Phase: 4
|
||||
Plan: Not started
|
||||
Phase: 04 (cli-scaffolding-i18n-and-mail) — EXECUTING
|
||||
Plan: 2 of 4
|
||||
Status: Ready to execute
|
||||
Last activity: 2026-09-18 -- Phase 4 planning complete
|
||||
Last activity: 2026-09-18
|
||||
|
||||
Progress: [██████████] 100%
|
||||
Progress: [████████░░] 82%
|
||||
|
||||
## Performance Metrics
|
||||
|
||||
@@ -58,6 +58,7 @@ Progress: [██████████] 100%
|
||||
| Phase 03 P03-02 | 5 min | 2 tasks | 8 files |
|
||||
| Phase 03 P03-03 | 8 min | 2 tasks | 17 files |
|
||||
| Phase 03 P03-04 | 15 min | 2 tasks | 15 files |
|
||||
| Phase 04 P01 | 11 min | 3 tasks | 14 files |
|
||||
|
||||
## Accumulated Context
|
||||
|
||||
@@ -101,6 +102,9 @@ Recent decisions affecting current work:
|
||||
- [Phase 03]: Phase 3 gate inlines TestParitySynthetic and CLI record/replay; PHP --fresh-php stays the Phase 2 sign-off because four wishlist album_count routes currently fail on live PHP — check-phase2.sh --fresh-php reports 150/154 on wishlist album_count expected 1 vs live 2. Phase 3 did not change PHP, tide, or those fixtures, so the Phase 3 gate must not fail on that drift.
|
||||
- [Phase 03]: testcontainers-go v0.44.0 is the STACK-named test dependency for framework lagoon isolation tests, matching the app TestMain — DATA-01 isolation tests need a real ICU pl-PL Postgres. The app already used testcontainers; the framework module now pins the same STACK versions so lagoon tests do not share the app TestMain.
|
||||
- [Phase 03]: High-severity T-03-01 through T-03-04 and T-03-06 are closed with failing-when-broken tests; token issuing remains test-only until Phase 7 — Roadmap required a security review of the JWT guard. 03-SECURITY-REVIEW.md maps each threat to a passing test; minting tokens through a production API is out of this slice.
|
||||
- [Phase 04]: registry.gen.go is regenerated by scanning Code generated by summer make files, not by rewriting plugin.go — D-12: handwritten plugin.go stays byte-identical; existing plugins get a one-time accessor hint
|
||||
- [Phase 04]: make:model table names are vendor_plugin_plural_snake with explicit gormigrate CREATE/DROP TABLE — D-13: timestamps on the model; --no-migration omits only the create-table file
|
||||
- [Phase 04]: models sibling-import check runs in build.App before go build and reports plugin ID, file, and import — D-11: limited to classes/controllers/console/jobs/middleware/updates of the same plugin module
|
||||
|
||||
### Pending Todos
|
||||
|
||||
@@ -122,6 +126,6 @@ Items acknowledged and carried forward from previous milestone close:
|
||||
|
||||
## Session Continuity
|
||||
|
||||
Last session: 2026-09-18T00:14:26.005Z
|
||||
Stopped at: Phase 4 context gathered
|
||||
Resume file: .planning/phases/04-cli-scaffolding-i18n-and-mail/04-CONTEXT.md
|
||||
Last session: 2026-09-18T11:42:10.258Z
|
||||
Stopped at: Completed 04-01-PLAN.md
|
||||
Resume file: None
|
||||
|
||||
Reference in New Issue