docs(state): record 04-01 completion and advance to plan 02

Mark CLI-02 complete, log scaffolding registry and leaf-check
decisions, and move Phase 4 progress to 1/4 plans.

Co-authored-by: Cursor <cursoragent@cursor.com>
This commit is contained in:
Jakub Zych
2026-09-18 13:42:34 +02:00
parent 6ce67a5d5b
commit e7dba5c4fb
3 changed files with 20 additions and 16 deletions

View File

@@ -155,7 +155,7 @@ Plans:
**Wave 1**
- [ ] 04-01-PLAN.md — Generate compiling plugin artifacts, registry and model import checks
- [x] 04-01-PLAN.md — Generate compiling plugin artifacts, registry and model import checks
**Wave 2** *(blocked on Wave 1 completion)*
@@ -367,7 +367,7 @@ Phases execute in numeric order: 1 → 2 → 3 → 4 → 5 → 6 → 7 → 8 →
| 1. Framework kernel foundation | 4/4 | Complete | 2026-09-16 |
| 2. API parity harness bootstrap | 5/5 | Complete | 2026-09-17 |
| 3. First vertical slice — genres end to end | 4/4 | Complete | 2026-09-17 |
| 4. CLI scaffolding, i18n and mail | 0/TBD | Not started | - |
| 4. CLI scaffolding, i18n and mail | 1/4 | In Progress| |
| 5. Data layer full fidelity | 0/TBD | Not started | - |
| 6. HTTP routing, auth groups and rate limiting | 0/TBD | Not started | - |
| 7. User plugin and authentication | 0/TBD | Not started | - |