- 13-SECURITY-REVIEW.md: every T-13 threat with its strictest severity and
disposition, protecting code, named tests and the 31 removal checks,
all failing as required; the CSV export logging fix and the Phase 9
route inventory update
- 13-VALIDATION.md: per-task map 13-01-T1 to 13-06-T3 all green, the gate
command, coverage per package, Wave 0 ticked, status validated
- REQUIREMENTS.md: API-03, API-04, API-06 and API-07 complete
- deferred-items.md: 13-06 findings (process-wide job dispatcher, scalar
mapping body, tmpfs quota)
- Phase 13 repos name sm-user-plugin and summercms.go
- wishlist match/apply-release, the credential /test routes and the CSV
Discogs pick move to Phase 14 (D-01, D-02); notifications drop prune,
a Phase 14 console command (D-06); CSV and digest job bodies are Phase 14
- API-03, API-04, API-06, INTG-01 and INTG-02 follow; statuses untouched
- 12-SECURITY-REVIEW.md maps T-12-01..T-12-34 and T-12-SC to a named test
and 25 removal checks, all seen failing with the protection removed
- 12-VALIDATION.md validated with the final per-task map, nyquist_compliant
- REQUIREMENTS.md: API-01 and API-02 complete
Six plans (tracer generator, site UX and checkers, content A, content B,
acme/blog walkthrough, unit tests). SC4/DOCS-04 narrowed to docs/ pages per
D-18; README Go fence conversion logged as a todo.
Four plans: framework Go contracts and routes, framework SPA hosts,
Albums proof in fonoteka.go, and unit tests with the phase gate.
Adds ADMIN-07 to REQUIREMENTS.md and fills the Phase 10.1 roadmap goal,
success criteria and plan list.
Assembled avatar POST is 200. UAT is 12/12. AUTH-02 through AUTH-04
and I18N-02 are marked complete. Do not auto-advance.
Co-authored-by: Cursor <cursoragent@cursor.com>
Record the PHP-does-blacklist finding, the accepted Go 401 after logout,
and the 22-ported corpus so later phases do not revive the harness artifact.
Co-authored-by: Cursor <cursoragent@cursor.com>
- Advance phase progress to 8 of 11 plans
- Record transition-address security decisions and execution metrics
- Mark HTTP-07 complete in requirements tracking
Mark CLI-02 complete, log scaffolding registry and leaf-check
decisions, and move Phase 4 progress to 1/4 plans.
Co-authored-by: Cursor <cursoragent@cursor.com>
Tasks completed: 2/2
- Initialize the real app database through plugin migrations
- Serve the seeded genre list behind real cross-plugin JWT middleware
SUMMARY: .planning/phases/03-first-vertical-slice-genres-end-to-end/03-01-SUMMARY.md
Co-authored-by: Cursor <cursoragent@cursor.com>