Jakub Zych
bc17c3decb
chore: merge executor worktree (worktree-agent-01a0ba96)
2026-09-19 19:26:53 +02:00
Jakub Zych
1f56a9ee1c
docs(06-01): complete guard registry and dual-group genres plan
2026-09-19 19:24:03 +02:00
Jakub Zych
cca4ec3a8b
docs(06-04): complete SSRF-guarded fetch helper plan
...
- Record fetchguard.Fetch dial-time SSRF helper, typed reasons, and TDD commits
2026-09-19 19:03:20 +02:00
Jakub Zych
ecab09c37a
docs(06): finalize phase plan after verification
2026-09-19 17:16:58 +02:00
Jakub Zych
ad3d6f7f84
docs(06): revision pass 1 - resolve Limiter naming collision and add plugin-facing house-middleware capability
2026-09-19 17:13:02 +02:00
Jakub Zych
c4f406bb64
docs(06): create phase plan
2026-09-19 16:58:48 +02:00
Jakub Zych
6a9f5e1b47
docs(05): add code review fix report
2026-09-19 15:41:27 +02:00
Jakub Zych
c0b2b6db08
docs(phase-6): add validation strategy
2026-09-19 15:36:23 +02:00
Jakub Zych
e9c2f25ebe
docs(06): research HTTP routing, auth groups and rate limiting
2026-09-19 15:35:20 +02:00
Jakub Zych
07df9b1e74
docs(state): record phase 6 context session
2026-09-19 14:04:36 +02:00
Jakub Zych
820d17c6c3
docs(06): capture phase context
2026-09-19 14:04:36 +02:00
Jakub Zych
ab4ac856da
docs(05): add code review report
2026-09-19 00:20:17 +02:00
Jakub Zych
bbee45c5f4
docs(05): add code review fix report
2026-09-18 23:53:21 +02:00
Jakub Zych
ba8a822149
docs(phase-5): evolve PROJECT.md after phase completion
2026-09-18 21:11:43 +02:00
Jakub Zych
0056c35cb0
docs(phase-5): complete phase execution
2026-09-18 21:11:43 +02:00
Jakub Zych
cd546dae1d
docs(05): add code review report
2026-09-18 21:11:11 +02:00
Jakub Zych
38cd4c6f50
docs(05-06): record plan close-out in STATE and ROADMAP
...
- Phase 5 plan 6 of 6 complete and ready for verification
- Record 23 min / 3 tasks / 12 files and the fill-boundary test decisions
2026-09-18 20:56:10 +02:00
Jakub Zych
ba3efccadd
docs(05-06): complete fill-fuzz hidden-marshal security-review plan
...
- Record fuzz, hidden-marshal, public_token, attach, and security-review outcomes
- Note module-boundary placement of the models.All() walk
2026-09-18 20:54:10 +02:00
Jakub Zych
e0a11c3ea0
docs(05-06): security review of fill and encryption boundaries
...
- Map T-05-01 through T-05-24 to a passing test or restated accept rationale
- Enumerate every .Reveal() call site; none are on log or serialize paths
- Confirm zero AutoMigrate production calls and no Association Mode pivot writes
2026-09-18 20:51:35 +02:00
Jakub Zych
67434f5185
docs(05-05): record plan close-out in STATE and ROADMAP
...
- Advance to plan 6 of 6; mark DATA-11 and CLI-03 complete
2026-09-18 20:28:00 +02:00
Jakub Zych
62f3ae563f
docs(05-05): complete remaining-models schema-diff fixture plan
...
- Record Task 1-3 commits, D-02 allow-list, and DATA-11 fixture isolation
2026-09-18 20:26:41 +02:00
Jakub Zych
678b216900
docs(05-04): record plan close-out in STATE and ROADMAP
...
- Advance to plan 5 of 6; DATA-08 marked complete
2026-09-18 20:05:58 +02:00
Jakub Zych
690aed2ea6
docs(05-04): complete attachments system_files blob and thumb plan
...
Tasks completed: 3/3
- Task 1: File, Thumb, bucket, system_files migration
- Task 2: delete lifecycle and static handler
- Task 3: Album/Collection MorphName
SUMMARY: .planning/phases/05-data-layer-full-fidelity/05-04-SUMMARY.md
2026-09-18 20:04:39 +02:00
Jakub Zych
b1b740c333
docs(05-03): record plan close-out in STATE and ROADMAP
2026-09-18 19:44:42 +02:00
Jakub Zych
76852e2d55
docs(05-03): complete secrets-slice encrypted credentials plan
...
- AES-256-GCM Encrypted, key:generate, Laravel helper, organisations, OAuth tables
2026-09-18 19:43:02 +02:00
Jakub Zych
a46c153480
docs(05-02): record plan close-out in STATE and ROADMAP
...
- Advance to plan 3 of 6 and mark DATA-04/05/07/09 complete
2026-09-18 19:25:21 +02:00
Jakub Zych
628cffd66f
docs(05-02): complete album-collection vertical slice plan
...
- Record migrations, Jsonable/MoneyString, Validate, write services, and hooks
2026-09-18 19:23:51 +02:00
Jakub Zych
06635f21cd
docs(05-01): record plan close-out in STATE and ROADMAP
...
- Advance to plan 2 of 6; 05-01 marked complete
- DATA-03, DATA-06, DATA-10 checked in REQUIREMENTS.md
2026-09-18 18:53:33 +02:00
Jakub Zych
87006d12d9
docs(05-01): complete Winter layout and lagoon primitives plan
...
Tasks completed: 4/4
- Folded-todo models-leaf probe
- Winter-directory plugin restructure
- lagoon Fill and lifecycle cascade
- Paginate, RegisterJoinTable, DATA-09 wording
SUMMARY: .planning/phases/05-data-layer-full-fidelity/05-01-SUMMARY.md
2026-09-18 18:49:59 +02:00
Jakub Zych
c85fa24936
docs(05-01): drop 27-migrations target and move HTTP fuzz to Phase 12
...
- DATA-09 and Phase 5 criteria follow D-01 squash and D-07 service-level fuzz
- Phase 12 inherits the write-endpoint DTO fuzz once HTTP exists
2026-09-18 18:48:08 +02:00
Jakub Zych
a9c77fcf49
docs(05-01): confirm models-leaf rule against three more plugins
...
- Probe keios.eu user, jz chat, and pxpx checkout for models→sibling uses
- Every live edge is a cast or service-calling hook; no "other" category
- Close folded todo verify-models-leaf-rule; bulk port may proceed
2026-09-18 18:37:26 +02:00
Jakub Zych
29b73b6892
docs(05): create phase plan
2026-09-18 18:06:55 +02:00
Jakub Zych
bbf49a910a
fix(05): revise plans based on checker feedback
2026-09-18 17:31:53 +02:00
Jakub Zych
2191e7a6d5
docs(phase-5): add validation strategy
2026-09-18 15:47:30 +02:00
Jakub Zych
8d3d737682
docs(05): research data layer full fidelity phase
2026-09-18 15:46:29 +02:00
Jakub Zych
30c8cb46ab
docs(state): record phase 5 context session
2026-09-18 15:23:21 +02:00
Jakub Zych
c3e9eae083
docs(05): capture phase context
2026-09-18 15:23:21 +02:00
Jakub Zych
e5f90c57c5
docs(phase-4): evolve PROJECT.md after phase completion
2026-09-18 14:23:56 +02:00
Jakub Zych
d08675aaff
docs(phase-4): complete phase execution
2026-09-18 14:23:56 +02:00
Jakub Zych
6954c5e5f2
docs(04): add code review report
2026-09-18 14:19:37 +02:00
Jakub Zych
f6af510716
docs(state): record 04-04 completion and mark phase 04 complete
...
Co-authored-by: Cursor <cursoragent@cursor.com >
2026-09-18 14:14:13 +02:00
Jakub Zych
9a69353220
docs(04-04): complete unit tests and Mailpit plan
...
Tasks completed: 3/3
- Close scaffold and CLI command boundary coverage
- Close translation lookup and catalog boundary coverage
- Close mail safety, driver, and Mailpit receipt coverage
SUMMARY: .planning/phases/04-cli-scaffolding-i18n-and-mail/04-04-SUMMARY.md
Co-authored-by: Cursor <cursoragent@cursor.com >
2026-09-18 14:13:14 +02:00
Jakub Zych
71f13f5620
docs(state): record 04-03 completion and advance to plan 04
...
Co-authored-by: Cursor <cursoragent@cursor.com >
2026-09-18 14:03:43 +02:00
Jakub Zych
3b476cbf55
docs(04-03): complete postcard mail plan
...
Tasks completed: 3/3
- Render and send one registered template through memory
- Register plugin layouts and publish the mailer at Boot
- Add config-selected log and SMTP delivery
SUMMARY: .planning/phases/04-cli-scaffolding-i18n-and-mail/04-03-SUMMARY.md
Co-authored-by: Cursor <cursoragent@cursor.com >
2026-09-18 14:03:11 +02:00
Jakub Zych
a6555c4606
docs(state): record 04-02 completion and advance to plan 03
...
Co-authored-by: Cursor <cursoragent@cursor.com >
2026-09-18 13:54:05 +02:00
Jakub Zych
c203bdfc54
docs(04-02): complete i18n phrasebook plan
...
Tasks completed: 3/3
- Load a namespaced translation from an embedded plugin
- Select CLDR and Laravel plural forms with PHP parameters
- Apply configured locale fallback and missing-key behavior
SUMMARY: .planning/phases/04-cli-scaffolding-i18n-and-mail/04-02-SUMMARY.md
Co-authored-by: Cursor <cursoragent@cursor.com >
2026-09-18 13:53:31 +02:00
Jakub Zych
e7dba5c4fb
docs(state): record 04-01 completion and advance to plan 02
...
Mark CLI-02 complete, log scaffolding registry and leaf-check
decisions, and move Phase 4 progress to 1/4 plans.
Co-authored-by: Cursor <cursoragent@cursor.com >
2026-09-18 13:42:34 +02:00
Jakub Zych
6ce67a5d5b
docs(04-01): complete CLI scaffolding plan
...
Tasks completed: 3/3
- Prove and create the compiling Winter-shaped plugin path
- Generate model, migration, and command slices
- Generate jobs and admin controllers, then enforce model imports
SUMMARY: .planning/phases/04-cli-scaffolding-i18n-and-mail/04-01-SUMMARY.md
Co-authored-by: Cursor <cursoragent@cursor.com >
2026-09-18 13:42:00 +02:00
Jakub Zych
846e6d5b74
docs(04): create phase plan
2026-09-18 13:24:54 +02:00
Jakub Zych
a5c8e0e31b
docs(04): map validation to planned tasks
2026-09-18 13:24:01 +02:00