docs(35-08): record plan completion in state and roadmap
This commit is contained in:
@@ -1936,7 +1936,7 @@ Plans:
|
||||
**Requirements**: TBD
|
||||
**Depends on:** Phase 34
|
||||
**Context:** postcard already loads plugin templates and layouts from `views/mail/` (`pact.HasMailTemplates`, `postcard.BootPlugin`); this phase adds the editable database layer, admin screens and image handling on top. To confirm in discussion: partials (WinterCMS mail partials), preview and test send, per-locale variants, and whether the screens live in cabana or in a plugin.
|
||||
**Plans:** 7/9 plans executed
|
||||
**Plans:** 8/9 plans executed
|
||||
|
||||
Plans:
|
||||
**Wave 1**
|
||||
@@ -1961,7 +1961,7 @@ Plans:
|
||||
- [x] 35-07-PLAN.md — unit tests for both gaps and `scripts/check-phase35.sh` with a read-only scratch-modfile consumers stage
|
||||
|
||||
**Wave 8** *(gap closure CR-01, blocked on Wave 7 completion)*
|
||||
- [ ] 35-08-PLAN.md — URL-scheme check on decoded attribute values instead of the whole document, a site name never stops a send (dropped with a warning) and an unsafe one is refused on the Branding form, the inlined result never stops mail, literal footer (CR-01, WR-01, WR-05), decision note
|
||||
- [x] 35-08-PLAN.md — URL-scheme check on decoded attribute values instead of the whole document, a site name never stops a send (dropped with a warning) and an unsafe one is refused on the Branding form, the inlined result never stops mail, literal footer (CR-01, WR-01, WR-05), decision note
|
||||
|
||||
**Wave 9** *(gap closure tests, blocked on Wave 8 completion)*
|
||||
- [ ] 35-09-PLAN.md — regression and unit tests for CR-01, WR-01 and WR-05, new names required by `scripts/check-phase35.sh` (plus the IN-03 self-test fix), validation map
|
||||
|
||||
@@ -2,18 +2,18 @@
|
||||
msd_state_version: "1.0"
|
||||
milestone: v1.0
|
||||
current_phase: 35
|
||||
current_phase_name: mail-templates-and-layouts-editor
|
||||
current_phase_name: Mail templates and layouts editor
|
||||
status: executing
|
||||
stopped_at: Completed 35-07-PLAN.md
|
||||
last_updated: "2026-11-14T14:02:34.272Z"
|
||||
last_activity: 2026-11-13
|
||||
stopped_at: Completed 35-08-PLAN.md
|
||||
last_updated: "2026-11-14T14:32:00.743Z"
|
||||
last_activity: 2026-11-14
|
||||
last_activity_desc: Phase 35 execution started
|
||||
state_head: 6e8cead959c42abe21a0899cb47a8e593f7fd348
|
||||
state_head: c4d0bbecc42a90f9d6c33ede91ea02c56f6b9884
|
||||
progress:
|
||||
total_phases: 52
|
||||
completed_phases: 37
|
||||
total_plans: 304
|
||||
completed_plans: 291
|
||||
completed_plans: 292
|
||||
gsd_state_version: "1.0"
|
||||
milestone_name: milestone
|
||||
---
|
||||
@@ -25,14 +25,14 @@ milestone_name: milestone
|
||||
See: .planning/PROJECT.md (updated 2026-10-22)
|
||||
|
||||
**Core value:** An existing WinterCMS-shaped app can be ported plugin by plugin to a single Go binary without its frontend noticing: the PHP version's API contract is the acceptance test.
|
||||
**Current focus:** Phase 35 — mail-templates-and-layouts-editor
|
||||
**Current focus:** Phase 35 — Mail templates and layouts editor
|
||||
|
||||
## Current Position
|
||||
|
||||
Phase: 35 (mail-templates-and-layouts-editor) — READY TO EXECUTE
|
||||
Plan: 4 of 4
|
||||
Phase: 35 (Mail templates and layouts editor) — EXECUTING
|
||||
Plan: 2 of 9
|
||||
Status: Ready to execute
|
||||
Last activity: 2026-11-13 — Phase 35 execution started
|
||||
Last activity: 2026-11-14 — Phase 35 execution started
|
||||
|
||||
Progress: [████████░░] 82%
|
||||
|
||||
@@ -320,6 +320,7 @@ Progress: [████████░░] 82%
|
||||
| Phase 35 P05 | 28 min | 3 tasks | 29 files |
|
||||
| Phase 35 P06 | 33 min | 3 tasks | 34 files |
|
||||
| Phase 35 P07 | 49 min | 3 tasks | 11 files |
|
||||
| Phase 35 P08 | 24 min | 3 tasks | 22 files |
|
||||
|
||||
## Accumulated Context
|
||||
|
||||
@@ -1124,6 +1125,10 @@ Recent decisions affecting current work:
|
||||
- [Phase 35]: 35-07: check-phase35.sh consumers run each core plugin through a scratch -modfile (sibling go.sum merged with the framework's, GOWORK=off, GOPROXY=off) and refuse a sibling that is dirty before or after
|
||||
- [Phase 35]: 35-07: G-35-8 recorded as framework-closed with the plugin part deferred; UAT test 8 re-run scoped to the built-in layouts (default, system) with logo, site name and the button partial
|
||||
- [Phase 35]: 35-07: Branding site name with a URL scheme stays an open item; TestMailBrandSiteName pins the current behaviour (saved, preview refused)
|
||||
- [Phase 35]: 35-08: postcard checks URL schemes only in decoded URL-bearing attributes, CSS, comments and meta content (x/net/html tokenizer); text is not a URL, so prose site names no longer stop mail (CR-01)
|
||||
- [Phase 35]: 35-08: postcard.UnsafeText (new exported API) drops unsafe site names at render with a value-free rate-limited warning and backs the Branding 422 on site_name (mail.brand.site_name_unsafe)
|
||||
- [Phase 35]: 35-08: an inlined result that fails the safety check is sent un-inlined with the inline:<layout> warning; the footer partial's text argument prints the site name literally
|
||||
- [Phase 35]: 35-08: cabana settings Put localizes BeforeValidate refusal phrase keys, as controller saves do
|
||||
|
||||
### Pending Todos
|
||||
|
||||
@@ -1271,6 +1276,6 @@ Items acknowledged and carried forward from previous milestone close:
|
||||
|
||||
## Session Continuity
|
||||
|
||||
Last session: 2026-11-13T21:11:20.401Z
|
||||
Stopped at: Completed 35-07-PLAN.md
|
||||
Last session: 2026-11-14T14:31:37.513Z
|
||||
Stopped at: Completed 35-08-PLAN.md
|
||||
Resume file: None
|
||||
|
||||